Comprehensive assessment of the technical condition of the hydraulic structure on the Maly Chembar River in the Penza Region
https://doi.org/10.26897/1997-6011-2025-3-53-62
Abstract
The article is devoted to a comprehensive assessment of the technical condition of a hydraulic structure on the Maly Chembar River in the Penza Region. A detailed study of the hydraulic unit’s condition was conducted, including the earthen dam, spillway structures, and bottom outlets, to determine the residual resource of their components and identify safety deficiencies. During visual and instrumental inspections, significant defects were identified, such as subsidence of the dam crest, concrete corrosion, malfunction of hydraulic equipment, and siltation of the spillway bottom. The results of the study showed that the hydraulic structure is in a critical (emergency) condition, requiring immediate major repairs to prevent potential accidents. The need to strengthen the dam body, restore the functionality of the outlets, and develop an emergency action plan is emphasized. The study also includes calculations of the spillway capacity and filtration characteristics of the earthen dam, which allow for an assessment of current risks and propose measures to improve the condition of the hydraulic structure.
About the Authors
A. P. AkasovRussian Federation
Anton P. Akasov, CSc (Eng)
Author ID: 958277
413123, Engels-23, Saratov Region, Rabochy Posyolok Privolzhsky, Gagarin Street, 1
M. I. Morozov
Russian Federation
Maxim I. Morozov
413123, Engels-23, Saratov Region, Rabochy Posyolok Privolzhsky, Gagarin Street, 1
D. A. Grekov
Russian Federation
Dmitry A. Grekov
Author ID: 973060
413123, Engels-23, Saratov Region, Rabochy Posyolok Privolzhsky, Gagarin Street, 1
M. E. Kadomtseva
Russian Federation
Marina E. Kadomtseva, CSc (Econ)
WoS Researcher ID: AAO-4585-2020; Scopus Author ID: 57216494307
Author ID: 574194
413123, Engels-23, Saratov Region, Rabochy Posyolok Privolzhsky, Gagarin Street, 1
R. B. Tuktarov
Russian Federation
Renat B. Tuktarov, CSc (Agro)
413123, Engels-23, Saratov Region, Rabochy Posyolok Privolzhsky, Gagarin Street, 1
References
1. National standard of the Russian Federation GOST R70566-2022 “Reclamation systems and structures. Rules of inspection and monitoring of technical condition” (approved and put into effect by Order of the Federal Agency for Technical Regulation and Metrology dated December 16, 2022 No. 1522-st)
2. Seredovskikh B.A., Deryabina V.V., Yarosh D.A. (2024). Condition of water protection structures in the Khanty-Mansi Autonomous Okrug – Yugra for protecting the population and territories from hydrological hazards. Prirodoobustrojstvo No. 4, P. 83-91. https://doi.org/10.26897/1997-6011-2024-4-83-91
3. Kuznetsov D.A., Ivanova L.P. (2020). Diagnostics of the emergency condition of the earth-fill dam of the Kama Reservoir. Vodnoe Khozyaistvo Rossii No. 3, P. 55-67.
4. Smirnov A.V., Petrov K.I. (2023). Assessment of the technical condition of reservoir hydroelectric complexes under climate change (case study of the Volga-Kama Cascade). Gidrotekhnicheskoe Stroitel’stvo No. 5, pp. 34-42.
5. Kadomtseva M.E. (2024). Methodology for assessing the impact of climate change on the sustainable development of the agro-food complex. Saratov: Saratovskii Istochnik, 294 p.
6. The Code of rules of JV 58.13330.2019. Hydraulic structures. The main provisions of SNiP 33-01-2003, 2020, 35 p.
7. Tuktarov R.B., Akpasov A.P. A brief overview of the modern regulatory and methodological framework for engineering and hydrographic work on water bodies for the purposes of land reclamation and ways to improve it. // Moscow Economic Journal. 2023. Vol. 8, No. 6. DOI: 10.55186/2413046X_2023_8_6_288.
8. Talalaeva V.F., Baev O.A. (2024). Results of field surveys of the technical condition of hydraulic structures of the Chernozemelskaya irrigation and water supply system. Puty Povysheniya Effektivnosti Oroshaemogo Zemledeliya, Vol. 93, No. 2, P. 1-15.
9. Finagenov O.M., Shtilman S.G., Shulman A.M., Yudelevich (2021). Development of methods for assessing the reliability of hydraulic structures. Izvestiya Vserossiiskogo Nauchno-Issledovatel’skogo Instituta Gidrotekhniki im. B.E. Vedeneeva, Vol. 300, P. 7-20. EDN: IANMJK
10. National standard of the Russian Federation GOST R59873-2021. Hydroelectric power plants. Methodology for determining safety criteria for declared structures. – Introduction. 2022-01-01. Moscow: Standartinform, 2021. 24 p.
11. Code of Rules SP 421.1325800.2018 “Reclamation systems and structures. Rules of operation” M.: 2019. 83 p.
12. GTS Safety Declaration “GTS reservoir Node on the Maly Chambar River of the Belinsky district of the Penza Region” No. 23-23(01)0032-13-SHZ. Saratov. 2023.
13. Chernykh O.N., Burlachenko A.V. (2022). Ensuring the safety of hydraulic structures of a reclamation hydroelectric complex with an earth-fill dam: Methodological guidelines. Moscow: RGAU-MSHA, 172 p.
14. Code of Rules SP 421.1325800.2018 “Reclamation systems and structures. Operating Rules” (approved by Order of the Ministry of Construction and Housing and Communal Services of the Russian Federation dated December 24, 2018 No. 854/pr)
Review
For citations:
Akasov A.P., Morozov M.I., Grekov D.A., Kadomtseva M.E., Tuktarov R.B. Comprehensive assessment of the technical condition of the hydraulic structure on the Maly Chembar River in the Penza Region. Prirodoobustrojstvo. 2025;(3):53-62. (In Russ.) https://doi.org/10.26897/1997-6011-2025-3-53-62